Check the slab volume before comparing the supply price.
A metric example separates measured concrete, planning allowance and an AUD material subtotal.
A simple slab quantity begins with dimensions, not a square-metre price. For a uniform rectangular slab, multiply length by width by thickness, with all three expressed in metres. Convert a drawing thickness in millimetres before entering it: 150 mm is 0.15 m.
Keep the measured volume visible
A 10 m × 8 m × 0.15 m slab has a geometric volume of 12 m³. This example assumes a uniform section without deductions. Edge beams, thickened zones, steps, drops, rebates and openings need a defined measurement treatment; do not hide them in a general allowance.
Show the planning allowance separately
At an illustrative 5%, the quantity becomes 12 × 1.05 = 12.60 m³. The allowance is a planning input, not a design requirement or a specified wastage factor. Confirm what the project and supply arrangement actually need.
Apply a rate on the same basis
At an illustrative AUD 280/m³, the concrete material subtotal is AUD 3,528. This is not an Australian market average or supplier quotation. Check the required product, order size, quote validity, delivery basis and any separate services before comparing offers.
Complete the scope around the pour
Reinforcement, formwork, labour, pumping, testing, equipment, delivery and tax are outside that material subtotal. Confirm site access, handling and pour sequence with the responsible team. An apparent difference in supply rates may reflect different included services.
Changing the example rate from AUD 280 to AUD 300/m³ changes the 12.60 m³ material subtotal from AUD 3,528 to AUD 3,780. The AUD 252 difference is a sensitivity calculation, not a forecast or a claimed saving.